Harbor Ave

Shelby County, Tennessee
  • 37,700 tons of asphalt and months of hard work
  • Asphalt produced by our President’s Island plant and our crews maximized every workable day with 24-hour operations 
  • Project required significant roadway rehabilitation due to advanced deterioration
  • Bid in August 2024; notice to proceed received in late November
  • Aggressive 90-day contract timeline under winter conditions
  • Weather posed ongoing challenges, including low temperatures, rain, and snow
  • Weekly stakeholder coordination meetings ensured alignment and timely execution
  • Strong collaboration with the City of Memphis, SSR, and project partners supported on-time delivery
LOCATION
LOCATION

Memphis, Tennessee